New report calls on Indiana to pause controversial LEAP pipeline

The economic development project could divert billions of gallons of water from Lafayette to Lebanon.

TIPPECANOE COUNTY, Ind. — A new report is calling on state officials to put a hold on the entire LEAP project, which is being built in Boone County.

The economic development project could divert billions of gallons of water from Lafayette to Lebanon.

Monday morning, the Citizens Action Coalition released a report, citing severe deficiencies in Indiana's water and economic development policy. 

The state's largest consumer and environmental watchdog group says the LEAP project promotes bad public policy by treating water as an economic development tool, rather than an essential public resource that must be protected.

The report also details concerns of taxpayers being forced to pay for a lot of new infrastructure.

"This is probably the largest economic development project in the history of the state of Indiana, and it has enormous implications on our natural resources, on public health, on taxpayer/ratepayer wallets, and we think the public and the communities should be involved in these conversations in creating a path forward that protects our water, protects our communities and protect our dollars," said Kerwin Olson, with the Citizens Action Coalition.

On Dec. 4, Tippecanoe County commissioners voted to impose a moratorium that temporarily stops the project from moving forward.

The three-member commission voted unanimously to implement a nine-month moratorium that blocks high-volume water exports from Tippecanoe County. The approved resolution also temporarily prohibits the construction of high-volume radial collector wells, the type of wells that are needed to collect and pump water for the ambitious pipeline project.

Before the vote took place, commissioners told attendees they have authority to regulate excavating and drilling in the county and to regulate use of property that could endanger public health, safety and welfare. After the vote – which was met with applause from the crowd – commissioner Tom Murtaugh told 13News the action was intended to give state lawmakers time to pass a law that addresses controversial water projects.

“If for some reason the legislature does not act, then we can extend that moratorium. But our goal is to slow this down until we can get some data and legislation in place to protect the citizens of Tippecanoe County,” Murtaugh said.

RELATED: Tippecanoe County imposes 9-month moratorium to slow controversial LEAP pipeline

Leaders in Tippecanoe County have been concerned about the pipeline project since first learning about it a year ago. The project is being led by the Indiana Economic Development Corporation, which has already spent $10 million to study, design and plan the pipeline.

Despite the state’s extensive plans, Murtaugh and other local leaders have told 13News they only learned about the project second hand – not from the IEDC – and they say the state agency has not been fully forthcoming when it comes to the details of the project.

RELATED: 'Deeply concerning': Former IEDC president criticizes his former agency for LEAP pipeline project

13 Investigates has been trying to get those details for months, submitting multiple requests to the IEDC under Indiana’s Access to Public Records Act. The state agency has released only a handful of records, and most of those have important details about the pipeline project blacked out.

The IEDC is continuing to hide the vast majority of the records requested by 13News, including management plans, risk assessment plans, engineering schedules, sustainability summaries, environmental impacts, project maps, and at least two dozen other documents the state agency has already commissioned and paid for. An IEDC attorney told 13News he believes the agency has a right to withhold public documents that are considered deliberative.

13News has filed a formal complaint with the Indiana Public Access Counselor that alleges the IEDC is improperly withholding the records in violation of state law.

Credit: WTHR
The Wabash River stretches for 500 miles across Indiana, but it does not run through Boone County.

The IEDC’s proposed pipeline would divert up to 100 million gallons of water per day from an aquifer under the Wabash River to a massive, high-tech industrial project that IEDC has created in Boone County. The IEDC says the LEAP project outside of Lebanon would not have enough water if it is successful in attracting major high-tech industries. The pipeline would solve that problem, according to the IEDC, bringing in water from the north and then dumping the wastewater in the Eagle Creek reservoir basin to the south.

The IEDC says preliminary test results show there is ample water flow within Wabash River aquifers to supply the LEAP project in Boone County without impacting residents or businesses in Tippecanoe County.